Civil Engineering Transportations MCQ-4
a) 0.4 %
b) 0.6%
c) 0.8 %
d) 1.0 %
Ans: b
93. Which of the following represents hardest grade of bitumen ?
a) 30/40
b) 60/70
c) 80/100
d) 100/120
Ans: a
94. Penetration test on bitumen is used for determining its
a) grade
b) viscosity
c) ductility
d) temperature susceptibility
Ans: a
95. Bitumen of grade 80/100 means
a) its penetration value is 8 mm
b) its penetration value is 10 mm
c) its penetration value is 8 to 10 mm
d) its penetration value is 8 to 10 cm
Ans: c
96. RC-2, MC-2 and SC-2 correspond to
a) same viscosity
b) viscosity in increasing order from RC-2 to SC-2
c) viscosity in decreasing order from RC-2 to SC-2
d) none of the above
Ans: a
97. The recommended grade of tar for grouting purpose is
a) RT-1
b) RT-2
c) RT.3
d) RT-5
Ans: d
98. Softening point of bitumen to be used for read construction at a place where maximum temperature is 40° C should be
a) less-than 40°C
b) greater than 40°C
c) equal to 40°C
d) none of the above
Ans: b
99. For rapid curing cutbacks, the oil used is
a) gasoline
b) kerosene oil
c) light diesel
d) heavy diesel
Ans: a
100. The method of design of flexible pavement as recommended by IRC is
a) group index method
b) CBR method
c) Westergaard method
d) Benkelman beam method
Ans: b
101. The group index for a soil, whose liquid limit is 40 percent, plasticity index is 10 percent and percentage passing 75 micron IS sieve is 35, is
a) 0
b) 3
c) 5
d) 7
Ans: a
102. Bottom most layer of pavement is known as
a) wearing course
b) base course
c) sub-base course
d) subgrade
Ans: d
103. Flexible pavement distribute the wheel load
a) directly to subgrade
b) through structural action
c) through a set of layers to the subgrade
d) none of the above
Ans: c
104. The number of repetitions, which the pavement thickness designed for a given wheel load should be able to support during the life of pavement is
a) 1000
b) 10000
c) 100000
d) 1000000
Ans: d
105. Group index method of design of flexible pavement is
a) a theoretical method
b) an empirical method based on physical properties of subgrade soil
c) an empirical method based on strength characteristics of subgrade soil
d) a semi empirical method
Ans: b
106. Select the correct statement.
a) More the value of group index, less thickness of pavement will be required.
b) More the value of CBR, greater thick-ness of pavement will be required.
c) Minimum and maximum values of group index can be 0 and 20 respec-tively.
d) all of the above
Ans: c
107. If the group index value of subgrade is between 5 and 9, then the subgrade is treated as
a) good
b) fair
c) poor
d) very poor
Ans: c
108. Tyre pressure influences the
a) total depth of pavement
b) quality of surface course
c) both the above
d) none of the above
Ans: b
109. Rigidity factor for a tyre pressure greater than 7 kg/cm2 is
a) equal to 1
b) less than 1
c) greater than 1
d) zero
Ans: b
115. The critical combination of stresses for corner region in cement concrete roads is
a) load stress + warping stress frictional stress
b) load stress + warping stress + frictional stress
c) load stress + warping stress
d) load stress + frictional stress
Ans: c
116. Tie bars in cement concrete pavements are at
a) expansion joints
b) contraction joints
c) warping joints
d) longitudinal joints
Ans: d
117. The maximum spacing of contraction joints in rigid pavements is
a) 2.5 m
b) 3.5 m
c) 4.5 m
d) 5.5m
Ans: c
118. The maximum thickness of expansion joint in rigid pavements is
a) 0
b) 25 mm
c) 50 mm
d) 100 mm
Ans: b
119. The function of an expansion joint in rigid pavements is to
a) relieve warping stresses
b) relieve shrinkage stresses
c) resist stresses due to expansion
d) allow free expansion
Ans: d
121. The fundamental factor in the selection of pavement type is
a) climatic condition
b) type and intensity of traffic
c) subgrade soil and drainage conditions
d) availability of funds for the construction project
Ans: b
122. Most suitable material for highway embankments is
a) granular soil
b) organic soil
c) silts
d) clays
Ans: a
123. Maximum daily traffic capacity of bituminous pavements is
a) 500 tonnes per day
b) 1000 tonnes per day
c) 1500 tonnes per day
d) 2000 tonnes per day
Ans: c
124. The most suitable equipment for compacting clayey soils is a
a) smooth wheeled roller
b) pneumatic tyred roller
c) sheep foot roller
d) vibrator
Ans: c
125. The aggregates required for one kilometre length of water bound macadam road per meter width and for 10 mm thickness is
a) 8 cubic meter
b) 10 cubic meter
c) 12 cubic meter
d) 15 cubic meter
Ans: c
126. The camber of shoulders in water bound macadam roads is
a) equal to the cross slope of pavement
b) less than the cross slope of pavement
c) greater than the cross slope of pavement
d) zero
Ans: a
127. The binder normally used in flexible pavement construction is
a) cement
b) lime
c) bitumen
d) none of the above
Ans: c
128. In highway construction, rolling starts from
a) sides and proceed to center
b) center and proceed to sides
c) one side and proceed to other side
d) any of the above
Ans: a
129. For the construction
of water bound macadam roads, the correct sequence of operations after
spreading coarse aggregates is
a) dry
rolling, wet rolling, application of screening and application of filler
b) dry
rolling, application of filler, wet rolling and application of screening
c) dry
rolling, application of screening, wet rolling and application of filler
d) dry
rolling, application of screening, application of filler and wet rolling
Ans: c
130. In
the penetration macadam construction, the bitumen is
a) sprayed
after the aggregates are spread and compacted
b) premixed
with aggregates and then spread
c) sprayed
before the aggregates are spread and compacted
d) none
of the above
Ans: a
131. When
the bituminous surfacing is done on already existing black top road or over
existing cement concrete road, the type of treatment to be given is
a) seal
coat
b) tack
coat
c) prime
coat
d) spray
of emulsion
Ans: b
132. Which
of the following premix methods is used for base course ?
a) bituminous
carpet
b) mastic
asphalt
c) sheet
asphalt
d) bituminous
bound macadam
Ans: d
133. Select
the correct statement.
a) Quantity
of binder required for tack coat is less than that required for prime coat.
b) Prime
coat treatment is given for plugging the voids in water bound macadam during
bituminous road construction.
c) Seal
coat is the final coat over certain previous bituminous pavements.
d) A
bitumen primer is a high viscosity cutback.
Ans: d
134. The
suitable surfacing material for a bridge deck slab is
a) sheet
asphalt
b) bituminous
carpet
c) mastic
asphalt
d) rolled
asphalt
Ans: c
135. Which
of the following is considered to be the highest quality construction in the
group of black top pavements ?
a) mastic
asphalt
b) sheet
asphalt
c) bituminous
carpet
d) bituminous
concrete
Ans: d
136. The
thickness of bituminous carpet varies from
a) 20
to 25 mm
b) 50
to 75 mm
c) 75
to 100 mm
d) 100
to 120 mm
Ans: a
137. Which
of the following represents a carpet of sand-bitumen mix without coarse
aggregates ?
a) mastic
asphalt
b) sheet
asphalt
c) bituminous
carpet
d) bituminous
concrete
Ans: b
138. In
highway construction on superelevated curves, the rolling shall proceed from
a) sides
towards the centre
b) centre
towards the sides
c) lower
edge towards the upper edge
d) upper
edge towards the lower edge
Ans: c
144. The
camber for hill roads in case of bituminous surfacing is adopted as
a) 2%
b) 2.5%
c) 3%
d) 4%
Ans: b
146. The minimum design speed for hairpin bends in hill roads is taken
as
a) 20
kmph
b) 30
kmph
c) 40
kmph
d) 50
kmph
Ans: a
147. The drain which is provided parallel to roadway to intercept
and divert the water from hill slopes is known as
a) sloping
drain
b) catchwater
drain
c) side
drain
d) cross
drain
Ans: b
148. The walls which are necessary on the hill side of roadway
where earth has to be retained from slipping is known as
a) retaining
wall
b) breast
wall
c) parapet
wall
d) none
of the above
Ans: b
149. In hill roads the side drains arc provided
a) only
on the hill side of road
b) only
on the opposite side of hill
c) on
both sides of road
d) none
of the above
Ans: a
Post a Comment
Please do not enter any spam link in the comment box.